1300 727 023

Projects

Continuous Drying Kiln – Foundations Earthworks & Slab

Scope

CMC were awarded the foundation earthworks & slab from Hyne Timber in early 2021. The project scope included stormwater drainage, earthworks, unbound pavements, and detailed concrete foundation slab to enable the construction of a Continuous Drying Kiln (CDK).

Throughout the project, several other upgrades were raised by Hyne Timber in which CMC efficiently proceeded in consulting and constructing these works. Construction of a 400m3 concrete access road, 40m3 bearer stand stab and asphalt tie ins were included in these additional works which complemented the CDK.

Many uncontrolled construction complexities arose throughout the project including unknown underground services and having to work around on-site traffic, however working with the client and local subcontractors, the project was delivered safely and on time.

Major Quantities

  • 2,000m3 Concrete
  • 10,000t Pavement Materials
  • 1,000m Rail embedded in concrete
  • 52t of reinforced steel
  • 4200m3 of earthwork excavation
Hynes Tuan Timber Mill
4.9M
Hyne Timber
January 2021 - June 2021

Continuous Drying Kiln – Foundations Earthworks & Slab

Next Project

Previous Project